Cam Hoa solar power plant is the first solar power project in Ha Tinh province with a capacity of 50 MWp. The plant is connected to the national electricity system through a 110kV substation and a 110kV line longer than 17km from Cam Hoa commune to Cam Hung commune.
On June 13, 2019, Cam Hoa Solar Power Plant have finished testing and commissioning with NLDC and ready for the COD (commercial operation date). EITS., JSC proud to be a part of this project. We supplied configuration service for DCS/SCADA system of Solar Power Plant. Thanks to our partners for your trust and confidence in our service.