The installation of electrical panels at Phuoc Thai 1 has been completed

Phuoc Thai 1 Solar Power Plant Project – the first solar power project invested by EVN, is under urgent construction to be energized in July 2020. The project was started in September 2019, built in Phuoc Thai commune, Ninh Phuoc district, Ninh Thuan province. With a capacity of 50MWp, when put into operation, about 80.975 million kWh will be added to the national power system.

In this project, EITS.,JSC supply, install, and configure relay protections as well as SCADA/CSCS systems.
Besides, we also supply the service of design and manufacture of electrical panels which fully meet standards and customer requirements.

By May 2020, our engineers have completed the transportation and installation of electrical panel systems at the site. The coordination with the investor and testing team to carry out all necessary processes also has been done.