Configuration for SICAM PAS (Siemens) System in 110kV Truc Son Substation – Truc Son Solar Farm

Investor: TTC Group. Truc Son Solar Power Plant project was built in hamlet 5, Truc Son commune, Cu Jut district, this is the second solar power project built in Dak Nong province (previously the Factory project Cu Jut solar power). Truc Son 110kV substation is located within the site of the factory. Configuration services for: …

Configuration for SICAM PAS (Siemens) System in 110kV Truc Son Substation – Truc Son Solar Farm Read More »

Configuration for SICAM PAS (Siemens) System in 110kV Linh Dam Substation

Co-operation: Vengy Company. The T3 40MVA 115/38.5/23kV transformer in 110kV E1.26 Linh Dam substation has been put into operation, that contribute to strengthen the capacity of the national electricity transmission system. List of works: – Configuration for SIEMENS Sicam PAS system with new IEDs from SIEMENS and TOSHIBA. – All new IEDs connect to system …

Configuration for SICAM PAS (Siemens) System in 110kV Linh Dam Substation Read More »

RTU of Vincom Plaze Tran Phu, Vinpearl Condotel Empire Nha Trang and Vinpearl Long Beach

Co-operation: A Chau., JSC. Vincom Plaza Tran Phu, Vinpearl Condotel Empire Nha Trang and Vinpearl Long Beach are construction projects of Vingroup, which is a famous Vietnamese conglomerate. List of works: – RTU Phoenix ILC 171 ETH controller configuration for medium voltage equipment. – Collect measurement signals. – Config the status and control equitments. – …

RTU of Vincom Plaze Tran Phu, Vinpearl Condotel Empire Nha Trang and Vinpearl Long Beach Read More »

SCADA System for 110kV Leveling to 220kV Long Bien Substation

Investor: EVNHANOI. Co-operation: Vengy Company. Within the framework of the project “New Construction of 110kV substation at 220kV Long Bien Supply Station”, the 110kV substation connecting 220kV Long Bien successfully energized, served the stable power supply for Long Bien district area and surrounding areas. List of works: – Configuration for BCU (GBU200 – Toshiba) to …

SCADA System for 110kV Leveling to 220kV Long Bien Substation Read More »

Operation Control Centre (OCC) in Northern Distribution Grid

Investor: Northern Power Corporation (EVNNPC). Currently, most SCADA systems in the transmission grid in Vietnam use IEC60870-5-101 communication protocol. However, this protocol has many limitations in establishing physical communication channels. IEC60870-5-104 protocol is being used instead of IEC 60870-5-101 protocol, which brings many advantages in deployment as well as high stability in transmission modes. List …

Operation Control Centre (OCC) in Northern Distribution Grid Read More »